Sheffield Street bridge over I-70 reopens

  • By Mike Jones August 30, 2013
Workers guide a concrete beam into place on the westbound side of Interstate 70 at Jessop Place as a truck speeds past in the eastbound lane during construction of a new bridge carrying Sheffield Street over the highway. - Observer-Reporter Order a Print

The Sheffield Street bridge that carries traffic over Interstate 70 at the Jessop Place exit reopened Friday morning following a six-month reconstruction project on the span.

The state Department of Transportation announced the opening of the $1.7 million bridge after the route was closed in early March so crews could replace the structurally deficient span in Canton Township.

The new bridge, which was completed by Golden Triangle Construction of Imperial two months before schedule, now has two 24-foot-wide lanes with 8-foot shoulders on either side. The original bridge was built in 1960, PennDOT spokeswoman Valerie Petersen said.

Motorists had been using a two-mile detour around the area during the construction project.

However, the construction project proved to be more cumbersome for truckers trying to make it to Jefferson Avenue. Since September 2009, the Jessop Place exit has been used by westbound truckers as a way to turn around to get onto Jefferson Avenue after that exit’s westbound off-ramp was closed to tractor-trailers. The construction forced truckers to continue on I-70 until the West Chestnut Street exit as the new detour.

It also created a longer detour for Canton Township volunteer firefighters coming from their station on Weirich Avenue.

The closure of the nearby Caldwell Avenue bridge over I-70 more than seven years ago left Sheffield Street as the best option for crews to respond to emergencies in the small sliver of the township southeast of the highway. But with the closure of Sheffield, Canton Township firefighters worked closely with their colleagues in Washington and North Franklin to help with the response. However, no major problems were reported during the construction period.

There is no timeline for reconstruction of the Caldwell Avenue bridge, which is located adjacent to the former Molycorp site, until the required environmental clearances are obtained to make sure there is no contamination in the area.

Mike Jones has been a news reporter since 2005, covering crime, state and municipal government, education and energy. In addition to working at the Observer-Reporter, he also has spent time at the Charleston (W.Va.) Daily Mail and He holds a journalism degree from West Virginia University.


blog comments powered by Disqus

Judge to trusts’ attorney: Recorder of deeds is not in contempt of court order

Police say North Strabane man assaulted wife as she bathed daughter

Cecil Elementary celebrates Thanksgiving feast

99-year-old Butsko Road bridge to be replaced with prefab structure

Roscoe resident petitions court to serve on school board

Water corrals to ease North Strabane traffic

Stoves, not turkey fryers pose biggest fire hazard

Fire sweeps through Independence Township apartment building

W&J student tackles gender, identity on campus

Hope for the holidays