West Penn Power updates completed reliability projects

3 min read

GREENSBURG – West Penn Power said Monday it is completing work on $17 million of electrical system projects as part of its 2016 Long-Term Infrastructure Improvement Plan, a multi-year program specifically designed to help reduce the number and duration of potential power outages experienced by the company’s 720,000 customers.

The projects, some of which are in Washington County, include installing enhanced protective devices on wires and poles, replacing or rebuilding electric lines, adding other special equipment, and installing automated and remote control devices.

“These projects benefit customers by complementing the work we already do each year to enhance the reliability of our electric system,” said David W. McDonald, regional president of West Penn Power. “Our goal is to make our system the best it can be when it comes to limiting the number and duration of outages our customers experience.”

The infrastructure improvement plan, approved earlier this year by the Pennsylvania Public Utility Commission, ultimately will result in an additional $88 million being spent through 2020 on targeted distribution infrastructure enhancement projects in the West Penn Power service area.

Projects completed this year include:

• Spending about $3.5 million to install new electronic circuit breakers, or reclosers, on 26 circuits in substations near Houston and Washington in Washington County, and Vandergrift, Jeanette and Lower Burrell in Westmoreland County. The devices can be operated remotely from the company dispatch center, providing operators the ability to restore power more quickly and efficiently than if a crew was needed to investigate a problem.

• Installing remote-controlled switches on higher-voltage distribution circuits at 45 locations both in substations and on overhead lines throughout West Penn Power’s service area at a cost of about $3 million. The new controls allow automatic and remote switching to help limit the number of customers affected when an outage occurs, and are engineered to shorten the duration of outages and allow for large blocks of customers to be more quickly restored.

• Spending about $2.7 million to install new fuses, wire and other equipment on more than 80 overhead circuits throughout West Penn Power’s service area, particularly at points where distribution circuits branch into smaller sections. The new equipment can automatically sense system irregularities and stop the flow of electricity, helping to limit the scope of outages and reduce the duration.

• Rebuilding portions of 38 distribution circuits at a cost of about $2.5 million, including replacing electrical components such as switches, cross arms, transformers, capacitors and insulators to help prevent outages caused by equipment issues throughout the company’s service area. The work also included the installation of animal guards.

• Replacing underground residential distribution cable with insulated, corrosion-resistant cable to help prevent outages and reduce the time necessary to locate and repair faults beneath the ground.  This year, about 1 mile of underground distribution cable was replaced in Quail Acres in North Strabane Township at a cost of about $440,000.

CUSTOMER LOGIN

If you have an account and are registered for online access, sign in with your email address and password below.

NEW CUSTOMERS/UNREGISTERED ACCOUNTS

Never been a subscriber and want to subscribe, click the Subscribe button below.

Starting at $3.75/week.

Subscribe Today